Project Management - Contracts & Outsourcing
76A project manager has to see a lot of activities in the nature of administrative, technical, socio-economic and environmental. If the manager is an engineer, supervision of technical jobs would be some-what easy. But other areas would receive less attention.
It is, therefore, imperative that the manager, in consultation with the board of directors, passes on some activities to contractors. This is known as out-sourcing which involves sub-contracting to a third party some of the activities like machine fabrication and installation, product design, manufacture and even marketing. Many multinational companies have outsourced routine jobs such as pay role, tax accounting, recruitment call center services and e-mails.
Advantages and Dis-Advantages
There are certain advantages in out-sourcing such as (i) The company can focus on its core activities, (ii) it would be cheaper and efficient, (iii) and over-heads would be reduced. But at the same time, there are dis-advantages like (i) threat to security and confidentiality, (ii) bad publicity, (iii) becoming hostage in hands of unscrupulous supplier, and (iv) hidden costs.
New types of out-sourcing
New type of out-sourcing are coming up, one is BOOT (Build, Own, Operate & Transfer). Laraib, a company, is developing a hydel power project, New Bong Escape. The company would use it own funds, carrying out all activities in its own name, operate the plant when completed, sell power to distribution company under usual tariff and transfer it to Government of Pakistan at the end of 25-year term. Many bridges and flyovers have been constructed under this arrangement and owners are happy with the toll tax being collected by their staff.
Other forms a are:
- BO ( Build and Operate ). Pakistan’s largest private power project, HUBCO, was constructed and operated by National Power of UK under this arrangement. Some call it Turn-key projects where sponsors would accept the project only when they are satisfied with its operational efficiency. It is like building a University Campus and attracting a desired number of students (say 2,000). There are penalties if there is a delay which is some time equal to Return on Investment made by the sponsors.
- BOO (Build, Own, Operate). A private party complete the project, owns it and puts into operations. There is some different from purely private investment as BOO is carried out for infra-structural projects like building a private railway line. Here government ensures that the land is obtained under some legal framework otherwise, a private party can never force the land owners to sell it to the project.
Type of contracts
When one outsources, one should pick up a suitable type of contract, some of which are listed below:
- Lump Sum Contract
- Unit Price Contract
- Cost Plus Contract
- Incentive Contracts
- Percentage of Construction Fee Contracts
To cut short, there two major type of contracts: (i) Lump Sum Contract (Fixed Cost) and (ii) Cost Plus % returns. In the latter, there is a danger of conflict of interest. If the contractor tries to be honest and efficient, it would reduce cost and thereby its returns. On the contrary, over-costing would lead to fat returns. If the contract is modified as cost plus a fixed fee, the drawback would be eliminated.
Advantages and dis-advantages of both are given below:
NATURE OF CONTRACTS
FIXED
| COST-PLUS
|
|---|---|
ADVANTAGES
| ADVANTAGES
|
Assurance of ultimate Cost
| Provides maximum flexibility to owners
|
Minimum Owner's follow-up
| Minimize Contractors Risk & Returns
|
Maximum incentives for quick completion
| Minimizes negotiations
|
Permits quick start and early finish
| |
DIS-ADVANTAGES
| DIS-ADVANTAGES
|
Long Negotiations
| No assurance of final cost.
|
Quality may not be assured
| No incentives to minimize Time and Cost
|
May prove costly due to built-in contingencies
| Conflict of Interest of Contractor
|
Frequent changes suggested by the owner or staff may lead to high cost and scope change.
|
CONSIDERATION
When procuring machinery or vehicle from outside, a project manager must spell out what he or she is looking for. Not only technical specification be given but also functional aspects be stated in details. This would help the supplier to offer a suitable or appropriate piece of machinery for long term business relations. This is explained below:
CommentsLoading...
sir,this article is very informative.all the things are explained by you in a very simple way.
thanks for sharing such great knowledge with us.
regards:
Muhammad Faisal
Respected Teacher, Very informative teacher.. and burger king vedio of answering machine.. that strategy is not the effective, i guess.. because it is creating a bad impact of burger king due to communication errors.. .
but, Very informative hub page Sir.. .
sir, u very well explained all the terminologies,outsourcing example & video are superb,it provided a practical knowledge thanks alot for sharing this with us
sir,the article is very informative, all the things are explained in a very simple way & easy to remember
Respected Sir,
It is one of your informative article that provides precious information regarding project management and outsourcing.
thanks for the hub.. didnt know the specific types of contract outsourcing
Read your previous hubs...your hubs really are so informative...I keep on scanning your other hubs also. Really great article you made. :)
SIR, ur article is very interesting. contracts & outsourcing are explained in very easy way.
thanku
regards
HIRA SAMI
it really works
gud work'







Rufi Shahzada 2 years ago
Dear Sir,
Thanks a lot for such a nice and informative HUB, well the advantages and disadvantages of outsourcing are explained so well.
The video of "BURGER KING outsourcing to INDIA" is just awesome example.
THANKS A MILLION!
RUFI SHAHZADA