Case Study: Using CPM or PERT in time planning & control
82For over three decades, I worked for a development bank. My main job was to evaluate proposals for setting up of industrial projects initially as an Officer and later as Head of the Division. I have many interesting stories to share in project planning and implementation. One such story is the success of Pakistan Mineral Water Corporation (PMWC) in water-bottling. The company no more exists. It has since been swallowed up by multinational brands of bottled-water like AVA, Aquafina & Culligan.
In early 1986, three companies, including PMWC, applied for water- bottling plants. The market justified only one. I called sponsors of the companies and told them that I would recommend the case of one which could demonstrate its ability to go into production before October 1987. “What is that for!!!” all spoke at the same time. “Well, as a bottlers you should know upcoming Cricket Cup at Karachi” I told them and added, “Anyone who catches the event would have an instant success.” Only one, J. Rashid of PMWC, turned up with a rudimentary sketch of CPM which convinced me of his ability to beat the deadline.
WHAT IS CPM?
Simply put, CPM stands for Critical Path Method used in planning and controlling time. It helps estimate time for project completion, pin-points activities critical for achieving the target. Above all, it gives a graphic view of the activities of a project which is easy to understand in one go.
TABLE #1
BACKGROUND INFORMATION
As per information provided by J. Rashid, the project required basic facilities like land, building and machinery which have been shown in Table #1 along with estimated time. As would be observed that after acquiring land, the company can go for three activities: (i) placing order for machinery, (ii) construction of building, (iii) placing order for plastic bottles for water filling.
When buildings are complete, machines can installed and the same time, racks can be erected for storing plastic bottles. Thus the company can go for trials runs as necessary pre-requisites are in order.
Format of a network or CPM varies. Basic structure is given in the text books or Software (MS Project 2007) which can be suitably modified. Personally, I like a detailed format for presentation.
Here each box or node has nine cells as shown in its legend. ES means Early Start while EF mean Early Finish.
In sketch # 1, some information has already been inserted about a particular activity such as ID, Description & Duration. The activities are also placed keeping their relationships in view.
Sketch # 1
FORWARD PASS
Let us start with ES & EF. This is simple except where we confront a Merge Event. We would insert Zero ( or expected date ) in the first cell of activity #1. Since duration for this activity is 1 month, the EF would be 0 + 1 = 1. Same would be carried for activities #2, #3 & #4 and EF worked out accordingly.
The ES of activity #5 would be 9, same as EF of its predecessor #3. It is natural; you cannot start erecting racks (#5) unless buildings (#3) are complete.
When you go next to activity #6, you would see two activities (#2 & #3) are merging. Obviously, you cannot start installation of machines (#6) unless the machinery has arrived as per order (#2) and buildings (#3) are complete. Here we would take maximum of EF of the both as both must be complete before #6 can be started. In the same way, we can complete rest of the diagram. We find that the project would take 19 months to be completed as shown in Sketch # 2 below:
Sketch #2
BACKWARD PASS
As the name implies, we move backward to the origin. In this example, the project completion time is 19 months. So its Early Finish (EF) or Late Finish (LF) must be the same. In other words, call it early or late, it must be finished by 19th month.
We start from last activity #8 and insert 19 in its LF cell. This activity has duration of 4 monthss. Calculating backward, we find that its LS should be 15th months (19 - 4 =15 ). In other, if #8 was started as late as on 15th months and it takes 4 months, it could still meet the deadline of 19 months.
We go back further and trace tails of any arrows touching #8. We find two, one linking with #7 (Store Raw Materials) and other with #6 (install machinery). We would put 15 in the LF Cells of #6 & #7. We can now calculate their LS by deducting from 15 their respective durations. For example, the LS of #6 should now be 9 (15-6=9).
We can continue likewise till we hit a "Burst Event" like #3 & #1. For explanation, #1 would be better as three activities are leading back to this activity. (There are three tails touching #1.) In such a situation, we shall take minimum of the LS of the three which is one month and it would be LF of #1. Why? The longest activity after #1 is #3. In order to enable #3 to start on time, it is essential that the preceding activity is completed well in time.
The complete working is shown in Sketch # 3 below:
Sketch # 3
WHAT IS A PERT?
PERT stands for “Project Evaluation and Review Technique”. It is almost the same as CPM except for the following differences:
- CPM is for repeated projects while PERT is for first-timers.
- CPM is used both for time and cost whereas in PERT only time is taken care of.
- Because CPM is for repeated projects, there is a track-record or database of previous projects. It enables the manager to be realistic in their estimates. For PERT, being for first time projects, one has to ask the knowledgeable persons to give time-estimates for each activity as to (i)Minimum time as in most favorable conditions, (ii) Maximum time as in most unfavorable conditions and (iii) Normal time. Thereafter a weighted average is calculated as shown in Sketch #4.
Sketch #4
- NEXT ARTICLE
I have since written the next hub which is about FLOATS. It uses the data given in this article and is one step forward.
OTHER ISSUES
Once time has been estimated, the rest is the same as in CPM.
In the upcoming articles, I would cover probabilities of project completion in different situations, relationship amongst activities, slacks and resource management.
vote upvote downshareprintflag
- Useful (6)
- Funny
- Awesome (1)
- Beautiful (2)
- Interesting (2)
CommentsLoading...
Its a realy very nice xplanation of PERT n CPM..i learned a lot for this practical xample as i have already learn these 2 mthod in ICMA ...but u desribed it very well ..nice case stdy
Thank You very much for sharing such a knowledgeable case.
I will ask you for help later on.........
Uptil now, each and every aspects of case, are clear.
Good article
25724
Thank you v. much.....
Am I rite if i interpret sketch # 3 as:
If the company starts late....It is Intalling racks, machinery and packing orders at the same time. Must start pacing orders by the 11th month and must finish it by the end of the 13th month....Must start install Machinery in Month 9.....and the company is instaaling machinery and packing orders in month # 11....
Thats really informative
I think that these pictorial views give me more understanding to have in your articles.
Regards,
Mubin Ashraf.
thank yo so much for sharing your articale
I've saved this case study for future reference. Thanks a lot to Mr. Hafeez Ur Rehman for this excellent work.Regards,Muhammad Fahad Khan.
very informative artical
why the most likely to happen take the weight 4
thanks for your care ,but iam asking why specialy 4 not 3 or 5 (i need an explanation from the point of statistical view)
really this text helped me alot
and cleared my doubts..
thanks .
A very good lecture well explained Thank You
very informative case study sir it would really help us in our course. Thank you for shearing this with us.
very informative article.
I have studied it deeply and come to know the soul of the article. thanks
Respected Sir, the article is really very good. Although, you had taught this article to us in the Class, but its really very interesting to read the material of which you had a little knowledge. This enhances your Knowledge more and more. Thanks alot for such nice Hubs.
Dear Readers,
I have just joined Hubpages..I think it has changed my life. I'm a British Engineer, working in China, and I'm helping to write a Guide to Project Planning. This material is inspirational. Don't worry I won't copy it!
But anyone interested in planning should check out www.planningplanet.com ...It is free and very useful to all planners worldwide. Furthermore they are creating an organization to get formal qualifications for planners and recognition for what we do. Please take time to have a look ..it may change your life like this site did for me.
best wishes to all, Rikbea
very helpful case study,thanks for sharing with us.
gud article
very informative sir
NICE CASE STUDY
ASA SIR
this case study is very informative and it helped me to understand all that points which i did nt get in class so thank you very much in order to share this case study.
Any body help me below mention question.
Identify the projects in which an organization can use PERT. Explain with examples.
AOA,
Its a realy very nice explanation of PERT and CPM.And also very informative case study.I thanks a lot For sharing your knowledge.















asifkamran 3 years ago
nice case